4.2.3.1 Engineering specifications
The organization shall have a process to assure the timely review, distribution and implementation of all customer
engineering standards/specifications and changes based on customer-required schedule. Timely review should be
as soon as possible, and shall not exceed two working weeks.
The organization shall maintain a record of the date on which each change is implemented in production.
Implementation shall include updated documents.
NOTE A change in these standards/specifications requires an updated record of customer production part approval when
these specifications are referenced on the design record or if they affect documents of production part approval process, such
as control plan, FMEAs, etc.
ขอแนวทาง หรือตัวอย่าง Procedure and Form ขอบคุณมากน่ะคับ โดน CARs